Savannah River Comcast Fiber

Earth View was requested by Comcast to install 4,800LF of 8” steel pipe in Savannah, GA. Located alongside a major highway system, EV was required to set up in the congested median of the highway interconnect.

Client
Comcast
Project Type
Trenchless Construction
Location
Savannah, GA
Year Completed
2019

Overview

Earth View was requested by Comcast to install 4,800LF of 8” steel pipe in Savannah, GA. Located alongside a major highway system, EV was required to set up in the congested median of the highway interconnect. Consequently, MOT was critical throughout the entire project. EV welded all of the pipes on site, handled all pipe support during pull back, and utilized Gyro due to navigable waters. The projected three-week drill was completed a week ahead of schedule.

EV welded all of the pipe on site, handled all pipe support during pull back, and utilized Gyro due to navigable waters.

The projected three week drill project was completed a week ahead of schedule.

Problems EV solved

Trenchless drilling

As a national leader in the trenchless drilling industry, Earth View tailored our approach to complete the project effectively and efficiently.

High-traffic area

The EV team was able to complete the project one week ahead of schedule on a heavily-trafficked roadway.